Capital Projects for 2017-2018

Current Capital Projects
Project Name Funding Source Phase/Status Expected Completion Estimate/Cost
Applied Tech Edison: Phase 3 Donor Design/Plan Review Winter 2017 $600,000
VSTA: Boilers & Central Plant Replacement (MF) HECC SHECC Design  Spring 2018 $623,000 
RDMT: Roof Replacement (3rd and 4th Floor) (MF) Cap. Imp. Fees Design  Spring 2018  $950,000
Child Care: Sidewalk HECC SHECC  Construction Fall 2017 $6,700
Dandini: Bus Stop Railing Replacement TBD Contracting Fall 2017 $6,000
Sub-Total       $2,185,700
Planning and Assessment Projects
Project Name Funding Source Phase/Status Expected Completion Estimate/Cost
Learning Commons Renovation Local CIP Design/Waiting on BOR approvals Fall 2018 $2,000,000
Sports and Health Complex TBD Waiting on BOR approvals   $14,000,000
Events/Auditorium/Technology Space (EATS) TBD  RFQ for Public Private Partnership TBD $33,000,000
CNA Relocation to MDWD TBD  Planning   $350,000
RDMT: Dental Expansion/Adopt-a-Vet Dental TBD  Planning    $1,400,000
RDMT: Server Room Upgrades TBD  Planning    $200,000
RDMT 211: HR Relocation TBD  Planning     
Student Services Upgrades Phase 2 TBD  Planning     
RDMT 200: Remodel TBD  Planning     
Applied Tech Edison: Indirect Cooling Machine Shops TBD  Hold   $75,000
Sculpture Garden TBD  Hold    
Memorial Wall TBD  Hold    
Sub-Total       $51,025.000
2017 CIP Submittals
Project Name Funding Source Phase/Status Expected Completion Estimate/Cost
Northern Nevada Advanced Mfg. Bldg.  State Not funded    $31,750,000 
Red Mountain: Shaft Repairs  State  Not funded    $295,311 
VSTA and Child Care: HVAC Upgrades  State  Not funded    $2,736,876 
Sub-Total       $34,782,187
Grand Total
Total       $87,992,887